Progress of the LTE Haute-Mauricie project Updates / Highlights 2022 May Beginning of the commissioning in Lac-Édouard for residential customers. April Arno Telecommunications is selected to build the tower in La Bostonnais. March Geotechnical studies are carried out for the La Bostonnais and La Tuque sites. February Installation of equipment at tour sites in Baie William and Festubert. January Testing of antennas and radios in Lac-Édouard for the coverage of residents. 2021 December Installation of equipment and antennas at the tower site in Lac-Édouard. November Construction of two towers in Parent and installation of power cables. October Installation of fiber optic cables in the Parent sector. September Construction of towers in Festubert, Lac Chat, Lac-Édouard, Baie William and Lac-à-Beauce. August Clearing work for access roads and tour sites in Tawachiche, Lac Mékinac and Lac Missionnaire. July Installation of fiber optic cables along Route 25 in Parent and along Chemin Tawachiche in Hervey-Jonction. June The firm Arno Telecommunications is selected for the construction of the towers in Parent and Rainbow Lake. May GD Télécom-Solution is mandated to install fiber optic cables between Hervey-Jonction and Lac-à-Beauce. April The firm Captel is selected for the construction of the towers in Lac-Édouard, Baie William and Lac-à-Beauce. March The firm Électro Saguenay is mandated to install fiber optic cables between La Tuque and Parent. February Geotechnical studies are carried out for the Parent, Rainbow Lake and La Bostonnais sites. January The firm Arno Telecommunnications is mandated for the construction and installation of the towers at Festubert and Lac Chat. 2020 December Commissioning of a new fiber optic link and connection of the municipal office in Lac-Édouard. November Deforestation work for the access roads and tower sites in Lac-à-Beauce and Lac-Édouard. October Installation of fiber optic cables and access shafts along Chemin du Lac-Édouard. September Start of public consultations for the La Tuque, La Bostonnais, Lac Missionnaire and Tawachiche towers. August Installation of fiber optic cables along Route 155 between La Tuque and Chemin du Lac-Édouard. July The foundations of the Saint-Joseph-de-Mékinac and Matawin towers are poured. June The CIMA+ firm is mandated for field surveys and engineering between La Tuque and Parent. May The Telecon firm is mandated to install fiber optic cables between La Tuque and Lac-Édouard. April The Captel firm is mandated for the construction and installation of the towers in Saint-Jospeh-de-Mékinac and Matawin. March Addition of a 15th tower to the project in the La Croche region, north of the city of La Tuque. February Installation of telecommunications equipment in Trois-Rivières. January Installation of telecommunications equipment and network management software in Montreal. Interested?Contact us! Name Business Email Phone Message Send 1-866-ECO-TEL1 1-866-326-8351 3400, boulevard L.-P.-NormandTrois-Rivières QC G9B 0G2