Highlights

2022

August
The company Électro-Saguenay has been selected to install fiber optic cables along Route 155 between kilometers 150 and 209.

July
The firm Arno Télécommunications has been selected to build two new towers in La Bostonnais and La Tuque.

June
Commissioning of the Lac-Édouard and Baie William towers;

May
Beginning of the commissioning in Lac-Édouard for residential customers.

Avril
Arno Telecommunications is selected to build the tower in La Bostonnais.

March
Geotechnical studies are carried out for the La Bostonnais and La Tuque sites.

February
Installation of equipment at tour sites in Baie William and Festubert.

January
Testing of antennas and radios in Lac-Édouard for the coverage of residents.

2021

December
Installation of equipment and antennas at the tower site in Lac-Édouard.

November
Construction of two towers in Parent and installation of power cables.

October
Installation of fibre optic cables in the Parent sector.

September
Construction of towers in Festubert, Lac Chat, Lac-Édouard, Baie William and Lac-à-Beauce.

August
Clearing work for access roads and tour sites in Tawachiche, Lac Mékinac and Lac Missionnaire.

July
Installation of fibre optic cables along Route 25 in Parent and along Chemin Tawachiche in Hervey-Jonction.

June
The firm Arno Telecommunications is selected for the construction of the towers in Parent and Rainbow Lake

May
GD Télécom-Solution is mandated to install fibre optic cables between Hervey-Jonction and Lac-à-Beauce.

April
The firm Captel is selected for the construction of the towers in Lac-Édouard, Baie William and Lac-à-Beauce.

March
The firm Électro Saguenay is mandated to install fibre optic cables between La Tuque and Parent.

February
Geotechnical studies are carried out for the Parent, Rainbow Lake and La Bostonnais sites.

January

The firm Arno Telecommunications is mandated for the construction and installation of the towers at Festubert and Lac Chat.

2020

December
Commissioning of a new fibre optic link and connection of the municipal office in Lac-Édouard.

November
Deforestation work for the access roads and tower sites in Lac-à-Beauce and Lac-Édouard.

October
Installation of fibre optic cables and access shafts along Chemin du Lac-Édouard.

September
Start of public consultations for the La Tuque, La Bostonnais, Lac Missionnaire and Tawachiche towers.

August
Installation of fibre optic cables along Route 155 between La Tuque and Chemin du Lac-Édouard.

July
The foundations of the Saint-Joseph-de-Mékinac and Matawin towers are poured.

June
The CIMA+ firm is mandated for field surveys and engineering between La Tuque and Parent.

May
The Telecon firm is mandated to install fibre optic cables between La Tuque and Lac-Édouard.

April
The Captel firm is mandated for the construction and installation of the towers in Saint-Joseph-de-Mékinac and Matawin.

March
Addition of a 15th tower to the project in the La Croche region, north of the city of La Tuque.

February
Installation of telecommunications equipment in Trois-Rivières.

January
Installation des équipements de télécommunication et logiciels de gestion du réseau à Montréal.